BCG VI, WORK EXPERIENCE
Experience in USVI
1989-91
-
Complete rebuild of CATV system in St. Thomas and St. John after Hurricane Hugo.
​
1995-96
-
Complete rebuild of CATV system on St. Thomas and St. John after hurricanes Marilyn and Bertha.
Nov. 2008 - Dec. 2009
-
Hurricane Repairs in St. Croix
Sept. 2010 - May. 2011
-
Hurricane Repairs in St. Croix and St. Thomas.
-
Aerial Fiber to Cell Towers in St. Croix
-
Sion Farm to Kingshill Fiber Project in St. Croix
-
Barren Spot HFC Upgrade in St. Croix
Jan. 2012 - 2014
-
Complete rebuild of the Telephone network with a HFC system in
St. Croix and St. John
​
2015 - 2017
-
Backbone fiber reinforcement, forced relocates to underground and extensions. Replacement of T-1 copper with fiber optic cable. Fiber placement to cell site St Thomas and St Croix.
-
Aerial and underground fiber construction for viNGN.
​
2017 - 2019
-
Hurricane repairs after Hurricanes Irma and Maria (St Thomas, St Croix and St John)
HFC Experience
2002 - 2004
-
Liberty Cablevision of PR. Approximately 2,300 miles. Drop-in upgrade of amplifier and line-extender modules, including return modules and activation. Existing actives, passives and cable was used. Return activation was done with return carrier generators. Fiber Optic cable run to nodes. Node Size approximately 2,000 homes passed with over 300 Power Supplies installed and activated.
​
2008 - 2011
-
Choice Cable. Upgrade in South and West areas of Puerto Rico. Approximately 4,500 miles of Plant. Fiber Optic cable run to nodes Approximately 600 homes passed. Total rebalance of all actives and approximately 700 nodes. Started drop-in upgrade October 2010 to upgrade actives to 750MHz. Change passives and cable that couldn’t pass signal to 750MHz. Over 250 Power Supplies installed and activated.
​
Senior Management Team Experience
2018 - Present
-
Critical Hub Fiber to the home in PR
-
T-mobile 5G Network Construction (Engineering, Fiber Construction and splicing, Antenna installation)
​
2009 - Present
-
PrepaNet Fiber plant extensions for the broadband network in the greater Puerto Rico to include Vieques.
2000 - 2001
-
Rebuild and upgrade of Framingham and Leominster, Mass., for Cablevision. Approximately 600 miles. On this upgrade all coaxial cable was replaced. Fiber Optic cable ran to nodes and nodes (optical receiver) installed, new cable activated and then drops swapped. Old cable then wrecked out. Node size approximately 300 homes.
​
1997-1999
-
HFC Upgrade (Retrofit) of Indianapolis, Indiana for Time Warner Cable. Approximately 2,500 miles.
​
1994-1996
-
HFC Upgrade (Retrofit),Charlotte, NC. for Time Warner Cable. Approximately 3,000 miles. Complete change-out of all passives and actives using existing coax cable. Fiber Optic Cable to nodes (600 homes). Complete change of nodes (up to 250 locations). All drops swapped, system activated and 24 hrs. standby on all service calls in node area.
1995 -1997
-
HFC Upgrade (Retrofit) Cincinnati, Ohio for Time Warner Cable. Approximately 4,000 miles.
​
1996 - 2000
-
HFC Upgrade (Retrofit) of Raleigh, NC, for Time Warner Cable. Approximately 12,000 miles.
​
​
Experience in USA​
2009 - 2010
-
Installed 16 Miles of Fiber Optic Interconnects from Time Warner Cable to Verizon Cell Sites – Underground and Aerial Construction $500,000
​
2008 - 2010
-
New Build, Commercial and Maintenance Projects for Aerial and Underground, Fiber and Coax Construction for Time Warner Cable $6,000,000
​
2006 - 2010
-
Drops and Installations Contractor for Time Warner $4,200,000
​
2009
-
Installed 100 Miles of Fiber Aerial and Underground Construction and Splicing for Time Warner’s Wayne County Upgrade - $3,000,000
​
2008
-
Installed 124 Miles of Fiber Aerial and Underground Construction and Splicing for the Elizabeth City Interconnect - $2,300,000
​
2008
-
Installed 120 Miles of Fiber Aerial and Underground Construction and Splicing for Time Warner’s Wilson County Upgrade - $3,000,000
​
2007
-
Installed 84 Miles of Fiber Aerial and Underground Construction and Splicing for Time Warner’s Franklin County Upgrade $2,000,000
​
2006
-
Installed 164 Miles of Fiber Aerial and Underground Construction and Splicing for Time Warner’s Hoke County Upgrade - $4,000,000
​
2004 - 2005
-
Installed 581 Miles of Fiber Aerial and Underground Construction and Splicing for Time Warner’s Johnston County Upgrade $8,000,000




BCG VI currently has people and equipment in the USVI. We have trained aerial and underground crews for coax, fiber splicers and activators ready to go for both St. Thomas and St. Croix. BCG VI also has the proven experience to move these resources into the USVI quickly. BCG VI has currently employed 30+ local residents to train along with our experienced techs to maintain a local work force.